Colorado Springs · Colorado Springs Utilities · 22 October 2026

Utilities sold its fiber network as a $200 million bargain. Its own records show what came next.

A year ago the Pikes Peak Bulletin laid out the lawsuits, delays and risk behind Colorado Springs Utilities’ fiber build. We checked its numbers against the Utilities Board’s packets and minutes and Council’s own meeting audio. Nearly all of them hold. Three are worth a second look.

In November 2025 Pam Zubeck of the Pikes Peak Bulletin reported that Colorado Springs Utilities’ citywide fiber network could involve up to $600 million in ratepayer money, that a fired contractor was suing for at least $61 million, and that Board member Nancy Henjum wanted to “better understand the benefit we’re getting.”

The fiber network belongs to Utilities, and the Utilities Board, made up of the nine City Council members, oversees it. Its paper trail sits in Board and Working Committee packets that rarely make the news: performance scorecards, budget variance tables, committee minutes. The Civic Desk searched those records, from 2023 through November 2025, for the fiber project, and checked what Utilities’ finance chief told Council in 2022 against the meeting video.

Here is what the record shows, and where it differs from what has been reported.

$19.4Mprojected 2025 fiber overspend, Utilities Board packet, Aug 2025
131days cash on hand at mid-2025, against a target of 151 to 160
17,319addresses delivered to Ting by November 2024
2027when Utilities said it must reach 150,000 connections

01The pitch, October 2022

On 25 October 2022, presenting Utilities’ 2023 budget to City Council, Tristan Gearhart, who described his view as that of the utility’s chief financial officer, laid out the fiber math. Utilities needed fiber for its own grid, he said. Building only that would cost about $400 million and stretch to about 2035. A bigger network with spare capacity to lease would cost about $600 million, built by 2028, and a signed lease would pay for much of it.

“The utilities has already secured a contract that will deliver between 2022 and 2047, $600 million worth of revenue.”Tristan Gearhart, City Council, 25 Oct 2022 · video at 3:00:55
“If I had a $400 million project that I needed to do for just the utilities purposes, I’m now able to take that and deliver it to our customers for $200 million.”Tristan Gearhart, 25 Oct 2022 · video at 3:01:36

Gearhart put about $78.7 million for fiber in the 2023 budget, after about $45 million in 2022. Asked whether the network would cost ratepayers, he said that for the $200 million project through 2028, “we don’t anticipate a rate increase for customers related to that” (3:04:21). The lease, he said, did not depend on how many people buy internet service:

“The way that we’ve established the contract with our anchor tenant is not dependent on market saturation, people that do sign up for that or not. We deliver addresses that have the availability to get that internet and we receive revenue.”Tristan Gearhart, 25 Oct 2022 · video at 3:06:22

Councilmember Dave Donelson added a guarantee: “If our anchor tenants decides they don’t want to do this anymore, legally they still have to pay us” (3:10:51). The anchor tenant is Ting, the fiber internet business of Tucows. In January 2025 staff told Council that Utilities recovers its costs from Ting “by addresses and as well as by fiber huts,” under “three different tiers of lease revenue” (14 Jan 2025, 6:39:54). The dollar terms of those tiers have not been presented in any public Board record we found.

Quotes in this section were checked against the meeting audio, not only the automated transcript.

02What happened to the schedule

The Board tracks the fiber build on a scorecard that averages a cost index and a schedule index; 1.0 means on plan. At the end of 2023 the cost index was 1.23 and the schedule index was 0.42, meaning the work was well behind schedule. The scorecard did not hide why.

“The primary reason for this measure not meeting expectations is the project is behind schedule. The contractor has failed over numerous portions of their contract deliverables.”Utilities Board packet, 20 Mar 2024 · page 44

Utilities issues a $27,754,636 task order for “FHR 1 Fiber Network Construction Services” and $3,981,852 for fiber hut buildings.Board packet, 19 Apr 2023, p. 17

Fiber scorecard 0.83 against a target of 0.95 to 1.05: Does Not Meet Expectations.Board packet, 20 Mar 2024, p. 44

Staff tell a Board committee that the previous contractor delivered 9,525 addresses in 18 months; the current one delivered 7,794 in seven. Three new contractors started on 24 September, 12 November and 1 December 2024. Total delivered to Ting: 17,319. Spending so far in 2024: $82.5 million, with $217.7 million more expected through 2028 and a 2024–2030 capital estimate of $396 million. When members asked more, the City Attorney asked that questions be taken offline “due to confidentiality reasons.”Program Management Review Committee minutes, printed in the 18 Feb 2025 Working Committee packet, pp. 15–16

Utilities forecasts $20 million more for fiber in 2025 “to make up for estimated 18-month delay caused by contractor delivery issues that resulted in a combined $96M underrun to budget (2022 – 2024).” It cites “the termination of one contractor and addition of two contractors in late 2024.”Working Committee packet, 16 Jun 2025, p. 14

According to the minutes, CEO Travas Deal said the spending was planned and that “due to the first contractor defaulting,” Utilities hired three more contractors.Working Committee minutes, 18 Aug 2025, p. 1

The Board records never name the contractor. The Bulletin identified it as ADB Companies of Missouri, hired in August 2022, which sued Utilities in October 2024 seeking at least $61 million; Utilities countersued for $60 million. None of the court filings are in the records COS-GPT holds. The records also count the replacements three different ways: three new contractors (November 2024), one terminated and two added (June 2025), and three more hired (August 2025).

032025: the overspend and the cash

By mid-2025 the delay had become a cost. The Board’s August packet raised the fiber project’s 2025 budget from $63,045,000 to $82,455,368, an increase of $19,410,371 (p. 33). In November the increase stood at $20,161,781 (Working Committee packet, 7 Nov 2025, p. 18).

The same August packet shows what that did to Utilities’ cushion. Days cash on hand, how long Utilities could pay its bills from cash alone, fell to 131 at mid-year, against a projection of 157 and a target range of 151 to 160. The packet names four drivers (pp. 57–58):

Driver of the drop, mid-2025Amount
Projected fiber project overspend$19.4M
Developer fees (CIAC) under-collected$17.3M
Non-fuel operations and maintenance over budget$10.5M
Interest earnings below plan$5.7M

Two days earlier, at the Working Committee, Henjum asked how the fiber project affects days cash on hand and whether it was planned. According to the minutes, Chief Operations Officer Somer Mese said Utilities “is under contractual obligation to hit 150,000 connections by 2027 and each connection will provide revenue.” Henjum asked for a more in-depth review of the project, and Board member Bailey agreed. By November, Utilities forecast 146 days at year-end, five below target (7 Nov 2025, p. 85).

04Checking the Bulletin’s numbers

Most of the figures the Bulletin drew from Utilities match the records exactly. Three differ, and several come from sources outside the public Board record, such as court filings, Tucows’ financial reports and a university study.

A $19.4 million fiber “over spend,” 131 days cash on hand against a 151–160 target, and a $17.3 million developer-fee under-collection.All three are in the 20 Aug 2025 Board packet, pp. 57–58.

Matches the record

Utilities hired three contractors after cancelling one.Nov 2024 committee minutes; Aug 2025 minutes (“first contractor defaulting”).

Matches the record

Utilities budgeted $79 million for fiber in 2023 (from the City Auditor).Gearhart told Council “$78.7 million” on 25 Oct 2022.

Matches the record

2026 Utilities budget of $2.2 billion, up 23%.$2.24 billion against $1.83 billion in 2025, Utilities’ annual operating and financial plan.

Matches the record

The Ting contract requires 150,000 addresses by May 2028.The Aug 2025 minutes record Mese saying 150,000 connections by 2027. The year and the unit both differ; the lease itself would settle it.

Differs from the record

Utilities forecasts Ting will pay about $464 million over 25 years.In 2022 Gearhart said the contract would deliver $600 million from 2022 to 2047. The Bulletin reports that Tucows’ own SEC filing cites $593 million. Nothing in the record explains the gap.

Differs from the record

Residential bills rise 28.9% by 2029; commercial 25%; industrial 21.7%.The dollar increases match Utilities’ table exactly. The percentages are the five yearly steps added together, which understates the compounded rise. See the next section.

Differs from the record

The ADB and Metronet lawsuits, Ting’s $8 per address and $3.6 million in payments, Tucows’ losses, $14.7 million paid to The Broadband Group.Reported by the Bulletin from court filings, company reports and Utilities statements. None appear in the Board records COS-GPT holds.

Not in our records

05The rate plan already in place

Utilities’ rates for 2025 through 2029 were set at one Council meeting. On 12 November 2024 City Council adopted four resolutions setting electric (24-561), water (24-563), wastewater (24-647) and natural gas (24-649) rates. Each passed 8–0. Avila, Crow-Iverson, Donelson, Helms, Henjum, Leinweber, Risley and Talarico voted yes; O’Malley was excused.

A year later Utilities showed the Board what the plan does to a typical bill before fuel costs, which move separately through the electric and gas cost adjustments. Under the table, Utilities noted: “No new base rates need through 2029” (Working Committee packet, 18 Aug 2025, p. 98).

Typical bill, non-fuel20252026202720282029
Monthly bill$227.12$241.99$257.94$274.81$293.01
Rise that year–6.5%6.6%6.5%6.6%

Yearly base-rate increases behind the table: electric 6.5%, water 6.5%, natural gas 4.0%, wastewater 9.0%. Gas excludes a possible pipeline-safety (DIMP) rider.

That is the increase arriving in January. This week the Utilities Board advanced a $2 billion budget for 2027, which The Gazette reports is 10% smaller than this year’s, and KKTV reports the typical customer will pay $16 more a month in non-fuel charges, about $258. Utilities’ 2025 table gives the same step: $241.99 to $257.94, an increase of $15.95. Council reviews the budget starting 10 November; the rates themselves were decided in 2024.

06Adding up the increases

An earlier version of the plan, presented to the Board in August 2024, prices a sample monthly bill, fuel included, for each customer class from 2024 to 2029 (Board packet, 21 Aug 2024, p. 67). The plan’s yearly increases compound: each one applies to a bill that already went up. Adding the five percentages together gives a smaller number than the actual rise.

Sample bill20242029IncreaseSteps addedActual rise
Residential$245.96$325.75$79.7928.9%32.4%
Commercial$1,437.89$1,833.56$395.6725.0%27.5%
Industrial$44,787.97$55,406.06$10,618.0921.7%23.7%

Bill amounts and yearly percentages are from the Utilities table. The “Actual rise” column is our calculation: the 2029 bill divided by the 2024 bill. The Bulletin attributes its percentages to the City Auditor’s Office. These are sample bills for four services (electric, gas, water, wastewater); Utilities notes that real bills vary with use.

07Still unanswered

  1. Which deadline is it? 150,000 connections by 2027, as the August 2025 minutes record, or 150,000 addresses by May 2028, as the Bulletin reported from the contract?
  2. What will Ting pay? $600 million (2022 testimony), $593 million (Tucows, as reported) or about $464 million (Utilities’ forecast, as reported)? The lease’s dollar terms have not been presented in a public Board record we found.
  3. Did the in-depth review happen? Henjum requested it in August 2025; the Bulletin reported in November that it had not been scheduled.
  4. Where does the project stand in 2026? COS-GPT does not yet hold Utilities Board records after 7 November 2025, so this piece cannot say.

Ask COS-GPT

Each link opens COS-GPT with the question filled in. Answers cite the Board documents above.

How we did this

  • Council votes: roll calls from the City’s Legistar records. Board records: Utilities Board and Working Committee packets and minutes from 2023 through 7 November 2025, as published on csu.org. Page numbers refer to the PDFs linked above.
  • Council audio: quotes from 25 October 2022 and 14 January 2025 were checked against the Granicus meeting video, not only the automated transcript. Speakers are identified by the chair’s recognition on the recording.
  • The Bulletin’s, The Gazette’s and KKTV’s reporting is credited where used. Claims we could not check against public records are labeled as reported.
  • Calculations (the compounded bill increases) are ours and are labeled.
  • Absences (“not in our records”) mean nothing turned up in the sources listed here. Court filings, contracts and records after 7 November 2025 are outside them.